Case Study · Electronics Supply Chain

Sizing Capacity Before You Know the Peak
Capital, Lead Time and a Two-Year Product Life Cycle

An electronics manufacturer had to commit capital to overseas component capacity before anyone knew how big the product would be. Lead times ran three to six months, and the product would be gone in two years. A model of the supply chain put a cost on being wrong in either direction before the money was spent, and tested what flexible ordering and expediting could recover.

Sector
Consumer electronics
The decision
How much component capacity to commit to up front
Scope
Overseas component plant, ocean freight, US assembly, distribution
What it was worth
The cost of over- and under-forecasting, priced before the commitment
Evidence
Project record

Three problems that make each other worse

Key components were made overseas and shipped to a US assembly plant, which fed the distribution centers. Loading, ocean transit and unloading, including customs, took 30 days. Three problems fed into each other:

Make componentsOverseas plant; capacity committed before launch
Ship by sea30 days including customs
Assemble unitsUS plant; safety stock sits here
DistributeDistribution centers to customer inventory
Expedite — air freight straight to assembly when demand spikes

Crossing capacity with demand

The model’s inputs were combinations of life-cycle demand and forecast. Three capacity commitments were crossed with three ways actual sales could turn out, including the one where the forecast was right.

Three capacity levels against three sales outcomes over a product life cycle Monthly sales over a two-year life cycle rise to a peak and fall away. Sales outcome B matches the forecast. Outcome A peaks above every capacity level; outcome C peaks just above the lowest. Capacity 1 sits above the forecast peak, capacity 2 at it, capacity 3 below it. Capacity 1 (high) Capacity 2 (medium) Capacity 3 (low) Sales A Sales B = forecast Sales C Two-year product life cycle → Monthly sales
Three capacity commitments against three sales outcomes over the product’s life. Redrawn from the original project figure.

Every combination was simulated through the life cycle and scored on capital equipment cost, the cost of prebuilding inventory ahead of a peak the plant could not meet, total shipping cost, inventory at both the overseas plant and the US assembly plant, and customer service.

What each combination did

Sales A (high)Sales B (medium)Sales C (low)
Capacity 1 (high)Moderate prebuild during peakNo prebuild; capital somewhat excessiveNo prebuild; capital very excessive
Capacity 2 (medium)Massive prebuild during peakModerate prebuild during peakNo prebuild; capital somewhat high
Capacity 3 (low)Capacity cannot keep pace with salesMassive prebuild during peakModerate prebuild during peak

Idle capital Moderate prebuild Massive prebuild Lost sales

Even where capacity matched demand, the model still called for a moderate prebuild during the peak. Committing one level too low turned that into a massive prebuild, and two levels too low meant capacity could not keep pace at all. Committing too high avoided prebuilds and paid for it in idle capital. Prebuilding was the only way to cover a peak the plant could not meet, so a shortfall in capacity turned into inventory built and paid for ahead of the peak.

What flexible ordering and expediting were worth

With capacity fixed, the model tested two ways to live with the forecast error:

Flexible ordering

If the assembly plant could adjust its orders closer to the time of need, it could hold far less safety stock against long lead times. The model asked how much flexibility was enough: flexibility helps the customer, but it pushes cost and risk back onto the supplier. Flexible ordering became the main tool for cutting the large safety stock at the US assembly plant.

Expedited shipments

Air freight answers a demand spike far faster than a month at sea. The model weighed that against its extra shipping cost, alongside the inventory and customer service each option produced.

The same shape of decision turns up well beyond electronics: a seasonal product, a limited-time flavor, a launch with a short window. Wherever capacity has to be committed before demand is known and the peak sizes the plant, the useful question is not “what is the forecast?” but “what does it cost if the forecast is wrong, in each direction?”

Where this sits in ReliaSim

The question runs through the network: a supplier with committed capacity, a long lane, an expedite option, an assembly plant and its safety stock. ReliaSim’s supply chain modeling represents sites, lanes, demand, inventory and ordering in one model, and the simplest version of that chain, a supplier feeding a plant feeding a customer, runs in the browser today.

Open the supply chain demo

On attribution. This model was built by Simulation Dynamics, the team behind ReliaSim, on a commercial simulation platform. The account rests on our project record rather than a published paper, and the client is not named. The software in the sandbox did not produce these results.